DELIA LEBADA PROJECT
01/09/2025
SC Delia Lebada SRL is
acting as Developer & Construction Manager for Phase 1 of Lebada Lake
Residence development in Bucharest, Romania.
Phase 1 consists of
three 7-storey buildings of 60 apartments targeting middle-class buyers.
a) Building A5 is ready
and its apartments have been fully tabulated. 51 sale-purchase agreements have
already been executed and 4 promissory contracts. There are 5 apartments
remaining unsold.
b) Building A4 is ready
and its apartments have been fully tabulated. 48 sale-purchase agreements have
already been executed. Currently there are 4 promissory contracts signed with
clients. The rest of 8 unsold apartments will be finished when they will be
sold.
b) Building A3 is ready
and its apartments have been fully tabulated. 30 sale-purchase agreements have
already been executed. Currently there are 14 promissory contracts signed with
clients. The rest of 17 unsold apartments will be finished when they will be
sold.
d) Concrete structure works
at Buildings A2 and A1 underway. Currently working on the 7th level
slab on A2. Superstructure of A1 will be finished by April 2026.
e) All utilities have
been finished and A5-A4-A3 are fully functional with all the meters installed.
f) Interior roads
finished up to building A3. Promenade hard landscaping works (pavements,
exterior parking places) have finished; soft landscaping phase 2 has been
finalized.
So far, 129 sales have
been concluded on the three buildings. The economic uncertainty caused by
increased money cost and worldwide inflation have affected the sales trend.
Finally, 115 apartments have already been handed-over in both registered
buildings.